DIA has identified two different ways in which orderscan be placed. Each has slightly different implications
forordering process and documentation.
The DIESCON 3 BPA is based on Federal Supply Service (FSS) Information Technology (IT) schedule rates that have been established
between a contractor and the GSA. The GSA has determined that the rates for services contained in each contractor's IT
schedule price list are fair and reasonable and FSS orders are deemed competitive actions (per FAR6.102). This permits
the customer to make a schedule award or logical follow-on award (per FAR 8.404) without an additional competitive process.
However, the customer always has the option of making a competitive award, using a simple and easily tailored approach, after
requesting a technical and price quote from multiple DIESCON 3 BPA Holders.
The following table lists specific tasks involved in the
order process. The individual with principal responsibility
for each task is coded with a P. The individual with support
responsibility is coded with an S. Click on any step to move
to a detailed description of the order activity and required
documentation. Click here
to move to a graphic depiction of order process tasks. It is
suggested that anyone interested in using the DIESCON 3 BPA
also review the implementation plan appearing at the DIA
DIESCON 3 web site for an additional discussion of order
placement tasks.
|
1.
|
Define requirements. Identify
objectives and desired outcomes of the planned
engineering or technical services. Resolve as list
of requirements. Principal responsibility of
Government Project Manager. BPA Holder interaction
is permitted and encouraged.
|
|
|
|
|
2.a.
|
Develop statement of work
(SOW). Prepare a SOW that describes the
objective, scope, technical requirements,
deliverables, special provisions, and inspection
and acceptance procedures. Principal responsibility
of Government Project Manager. BPA Holder
interaction is permitted and encouraged.
|
|
|
|
|
2.b.
|
Develop statement of
objectives (SOO). A SOO is similar to a SOW, except that requirements are
stated as functional performance objectives rather
than prescribed technical tasks. For example, a SOO
requirement statement for a database application
might specify the need to support 20 concurrent
users, display query transaction results within 10
seconds, and update in real time. Encourages
competing contractors to propose innovative
solutions to user requirements. Principal
responsibility of Government Project Manager. BPA
Holder interaction is permitted and encouraged.
|
|
|
|
|
2.c.
|
Develop evaluation factors.
Develop brief list of factors to be used in determining the contractor
with whom the order will be placed. Principal
responsibility of Government Project Manager. BPA
Holder interaction is permitted.
|
|
|
|
|
2.d.
|
Develop selection
procedures. Outline suggested approach to the selection process.
Determine whether oral presentations should be
permitted. Principal responsibility of Government
Project Manager.
|
|
|
|
|
|
|
|
3.a.
|
Transmit to the Ordering Authority,
along with the SOO, evaluation factors, and
selection procedures. Internal DIA elements must
also enclose a DIA Form 520. Principal
responsibility of Government Project Manager.
Coordination with Ordering Authority may be
required.
|
|
|
|
|
3.b.
|
Identify alternate
contractors. For competitive award where the order
value is expected to exceed $500,000, visit
additional DIESCON 3 BPA Holder web sites to
identify one or more alternate contractors who
should be requested to submit a competitive quote.
Add names of the alternate contractors to
competitive quote request described in paragraph
3.c. above. Principal responsibility of Government
Project Manager.
|
|
|
|
|
4.
|
Secure funding commitment.
Affirm availability of appropriate funds to support
order. If customer is an agency external to DIA and
DIA ordering support is required, prepare and
transmit a MIPR to transfer funds to DIA. (DIA
recommends that non-DIA customers request approval
for local Ordering Authority, rather than using DIA
ordering support.) Principal responsibility of
Finance Office. Government Project Manager support
required.
|
|
|
|
|
|
|
|
6.
|
Submit quotation. Selected
DIESCON 3 BPA Holder or Holders respond
electronically in five business days with technical
and price quote. Technical quote follows prescribed
format that permits it to serve as project plan,
following annotation to reflect changes resulting
from discussions prior to order placement.
Principal responsibility of BPA Holder.
Coordination with Ordering Authority possible for
clarification of RFQ requirements.
|
|
|
|
|
7.a.
|
Review quote and affirm best
value contractor. Review BPA Holders'
technical and price quote. Determine that level of
effort and mix of labor quoted is fair and
reasonable for service being purchased. Discuss and
resolve problems with contractor. Principal
responsibility of Ordering Authority. Close
coordination with Government Project Manager
suggested.
|
|
|
|
|
7.b.
|
Use selection procedures to
review quotes. As appropriate, schedule presentations by DIESCON 3
BPA Holders who quoted against requirement.
Principal responsibility of Ordering Authority.
Coordinate with Government Project Manager as
appropriate.
|
|
|
|
|
7.c.
|
Apply evaluation factors
against quotes. Apply evaluation factors outlined in earlier step against
technical and price quotes. Document results for
order files. Principal responsibility of Ordering
Authority. Close coordination with Government
Project Manager suggested.
|
|
|
|
|
7.d.
|
Downselect to single best
value contractor. Integrate evaluation results and
determine contractor offering best value to
customer, based upon technical and/or price
factors. Document results for order files.
Principal responsibility of Ordering Authority.
Close coordination with Government Project Manager
suggested.
|
|
|
|
|
8.
|
Issue purchase order. Place
formal order with selected best value contractor.
Transmit order electronically and/or via hard copy
means. Also notify contractor telephonically.
Disseminate copies of order internally in
accordance with agency procedures. Principal
responsibility of Ordering Authority. Coordinate
with Government Project Manager as appropriate.
|
|
|
|
|
9.
|
Notify unsuccessful DIESCON 3
Holders. Inform each unsuccessful contractor who
submitted a quote of award decision. Express thanks
for time expended in responding to requirement.
Principal responsibility of Ordering Authority.
|